TABLE OF
CONTENTS
Introduction
Environmental Monitoring and Audit
Progress
Breaches of Action and Limit Levels
Construction Noise
Complaint Log
Notification of Summons and Successful
Prosecutions
Reporting Changes
Future Key Issues
Purpose of the report
Structure of the report
Background
Project Organization
Summary of Construction Works Undertaken
During Reporting Month
Construction Programme
Status of Environmental Licences, Notifications and Permits
Monitoring Requirements
Monitoring Location
Monitoring Equipment
Monitoring Parameters, Frequency and
Duration
Monitoring Methodology and QA/QC
Procedures
Maintenance and Calibration
Results and Observations
Event and Action Plan
4 ENVIRONMENTAL
SITE INSPECTION
Site Audits
Implementation Status of Environmental
Mitigation Measures
Solid and Liquid Waste Management Status
5 ENVIRONMENTAL
NON-CONFORMANCE
Summary of Exceedances
Summary of Environmental Non-Compliance
Summary of Environmental Complaint
Summary of Environmental Summon and
Successful Prosecution
Key Issues in the Coming Two Months
Monitoring Schedule for the Next Month
Construction Programme
for the Next Month
7 CONCLUSIONS
AND RECOMMENDATIONS
Conclusions
Recommendations
LIST OF
TABLES
Table I Summary Table for
Monitoring Activities in the Reporting Month
Table II Summary Table for Events
Recorded in the Reporting Month
Table III
Summary Table for Site Activities in the coming Two Months
Table 2.1 Work Contracts undertaken in the
Reporting Month
Table 2.2 Key Contacts of the Project
Table 2.3 Summary Table for Major Site Activities
in the Reporting Month
Table 2.4 Status of Environmental Licenses,
Notifications and Permits
Table 3.1
Location for Noise Monitoring Stations
Table 3.2
Noise Monitoring Equipment
Table 3.3 Noise Monitoring Parameters, Duration and
Frequency
Table 3.4 Summary Table of Noise Monitoring Results
during the Reporting Month
Table 3.5 Observation at Noise Monitoring Stations
Table 4.1 Observations and Recommendations of Site
Audit
Table 4.2 Photographic Records of Measures
Table 6.1 Summary Table for Site Activities in the
coming Two Months
LIST OF
DRAWINGS
Drawing
no. 60335576/C1/C00/1031A-1051D Site
Layout Plan (Contract No. ND/2019/01)
Drawing
no. 60335576/C6/C00/1041 Site
Layout Plan (Contract No. ND/2019/06)
LIST OF
FIGURES
Figure 1 Location of Noise Monitoring
Station (Contract No. ND/2019/06)
Figure 2 Location of Noise Monitoring
Station (Contract No. ND/2019/01)
LIST OF
APPENDICES
Appendix A Construction Programme
Appendix
B Action and Limit
Levels
Appendix
C Copies of Calibration
Certificates
Appendix D Environmental Monitoring
Schedules
Appendix E Noise Monitoring
Results and Graphical Presentation
Appendix
H Summary of Exceedance
Appendix
J Environmental
Mitigation Implementation Schedule (EMIS)